Provision of these Regulations which fixes or determines the fees Previous Fee New Fee Percentage Increase
Schedule 1 Original approval Amendment of approval Renewal of approval Original approval Amendment of approval Renewal of approval Original approval Amendment of approval Renewal of approval
Fees under Mines and Quarries provisions                                                                                                   
Part 1                                                                                                   
Approval of explosives £309 £215 £75 £317 £221 £77 2.59 2.79 2.67
Part 2                                                                                                   
Break test shot            £238                       £244                       2.52           
Deflagration            £189                       £194                       2.65           
Detonator test (per 100 shots)            £1,453                       £1,492                       2.68           
Detonator delay time test (per 100 shots)            £1,150                       £1,181                       2.70           
Gallery shot            £272                       £279                       2.57           
Velocity of detonation test (per 3 shots)            £469                       £481                       2.56           
Part 3                                                           
Other testing not fixed in Part 2 Reasonable cost to the Executive of having the work carried out Reasonable cost to the Executive of having the work carried out            -           
Schedule 2                                                                                                   
Approvals under the Agriculture (Tractor Cabs) Regulations 1974                                                                                                   
Original approval of tractor cab            £443                       £455                       2.71           
Revision of an existing approval of a tractor cab

           £244                       £250                       2.46           
Schedule 3                                                                                                   
Approval under the Freight Containers (Safety Convention) Regulations 1984                                                                                                   
Approval of scheme or programme for examination of freight containers            £85                       £87                       2.35           
Schedule 4                                                                                                   
Applications under the Control of Asbestos Regulations 2006                                                                                                   
Table 1                                                                                                   
Licence for work with asbestos or renewal of licence            £1,023                       £1,050                       2.64           
Table 2                                                                                                   
Re-assessment of licence application            £276                       £283                       2.54           
Amendment of condition, or duration, of licence            £276                       £283                       2.54           
Amendment or replacement, of a licence            £74                       £76                       2.70           
                                                                                                             
           Basic X-Rays Laboratory tests Basic X-Rays Laboratory tests Basic X-Rays Laboratory tests
Schedule 5                                                                                                   
Examination or surveillance by an employment medical adviser                                                                                                   
The Ionising Radiations Regulations 1999                                                                                                   
(a) where surveillance is confined to examination of, and making entries in, records £34 £65 £38 £35 £67 £39 2.94 3.08 2.63
(b) in other cases £64 £65 £38 £66 £67 £39 3.13 3.08 2.63
Control of Asbestos

Regulations 2006

£64 £65 £38 £66 £67 £39 3.13 3.08 2.63
Control of Substances Hazardous to Health Regulations 2002 £64 £65 £38 £66 £67 £39 3.13 3.08 2.63
The Work in Compressed Air Regulations 1996 £64 £65 £38 £66 £67 £39 3.13 3.08 2.63
Schedule 6                                                                                                   
Medical surveillance under the Control of Lead at Work Regulations 2002                                                                                                   
On the first assessment of an employee (including any clinical medical examination and laboratory tests in connection with the assessment) £64                       £66                                  3.13           
On each subsequent assessment of an employee —                                                                                                   
(i) for laboratory tests where these are carried out £38                       £39                                  2.63           
(ii) for a clinical medical examination where this is carried out £38                       £39                                  2.63           
Schedule 7

Applications under the Ionising Radiations Regulations 1999 and the Radiation (Emergency Preparedness and Public Information) Regulations 2001

                                                                                                  
Table 1                                                                                                   
Group 1                                  Fee Hourly rate
Dose record keeping where the application is solely in respect of Group I function £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
Dose record keeping where the application for Group I functions is linked to an application for approval in another group £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
Group II                                                       
External dosimetry                                                       
(a) Whole body (beta, gamma, thermal neutrons) film £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
(b) Whole body (beta, gamma, thermal neutrons) thermoluminescent dosemeter (TLD) £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
(c) Whole body (neutron), other than sub-groups (a) or (b) £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
(d) Whole body, other than sub-groups (a), (b), or (c) £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
(e) Extremity monitoring £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
(f) Accident dosimetry, other than in the previous sub-groups £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
Group III                                                       
Internal dosimetry                                                       
(a) Bio-assay or in-vivo monitoring or air sampling £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
(b) For each additional technique £388 plus £123 per hour worked by Nuclear or Specialist Inspector £466 plus £126 per hour worked by Nuclear or Specialist Inspector            20.10 2.44
Type approval of apparatus under sub-paragraph 1(c)(i) or 1(d)(i) respectively of Schedule 1 to the Ionising Radiations Regulations 1999 £125 plus £123 per hour worked by Nuclear or Specialist Inspector £128 plus £126 per hour worked by Nuclear or Specialist Inspector            2.40 2.44
Table 2                                                       
Approval or reassessment of approval of Dosimetry Services granted under regulation 35 of the Ionising Radiations Regulations 1999 for the purposes of regulation 14 of the Radiation (Emergency Preparedness and Public Information) Regulations 2001 £1,724 plus £123 per hour worked by Nuclear or Specialist Inspector £1,770 plus £126 per hour worked by Nuclear or Specialist Inspector            2.67 2.44
Schedule 8                                                       
Applications etc concerning explosives and petroleum-spirit                                                       
Part 1                                                       
Licence to manufacture explosives not being ammonium nitrate blasting intermediate nor relating to on-site mixing £571 plus £115 per hour worked by Specialist Inspector £586 plus £116 per hour worked by Specialist Inspector            2.63 0.87
Licence to manufacture ammonium nitrate blasting intermediate £140 per hour worked £144 per hour worked            2.86           
Licence to manufacture explosives by means of on-site mixing £210 plus £115 per hour worked by Specialist Inspector £216 plus £116 per hour worked by Specialist Inspector            2.86 0.87
Renewal of any of the above licences £75 plus £115 per hour worked by Specialist Inspector £77 plus £116 per hour worked by Specialist Inspector            2.67 0.87
Licence to store explosives £571 plus £115 per hour worked by Specialist Inspector £586 plus £116 per hour worked by Specialist Inspector            2.63 0.87
Renewal of a licence £75 £77            2.67           
Varying a licence to manufacture explosives not being ammonium nitrate blasting intermediate or to store explosives £391 £401            2.56           
Varying a licence to manufacture ammonium nitrate blasting intermediate £140 per hour worked £144 per hour worked            2.86           
Transfer of a licence £48 £49            2.08           
Replacement of any licence referred to in Part 1 £48 £49            2.08           
Part 2                                                       
Licence to store explosives:                                                       
(a) one year's duration £120 £144            20.00           
(b) two years' duration £180 £216            20.00           
(c) three years' duration £225 £270            20.00           
Renewal of a licence:                                                       
(a) one year's duration £77 £79            2.60           
(b) two years' duration £128 £131            2.34           
(c) three years' duration £179 £184            2.79           
Registration in relation to the storage of explosives:                                                       
(a) one year's duration £72 £86            19.44           
(b) two years' duration £108 £129            19.44           
(c) three years' duration £145 £149            2.76           
Renewal of registration:                                                       
(a) one year's duration £36 £43            19.44           
(b) two years' duration £72 £81            12.50           
(c) three years' duration £105 £108            2.86           
Varying a licence:                                                       
(a) varying name of licensee or name of site £31 £32            3.23           
(b) any other kind variation Reasonable cost to the licensing authority of having the work carried out Reasonable cost to the licensing authority of having the work carried out            -           
Transfer of licence or registration £31 £32            3.23           
Replacement of licence or registration referred to above if lost £31 £32            3.23           
Part 3                                                       
Licence for importation of compressed acetylene £35 plus £115 per hour worked by Specialist Inspector £36 plus £116 per hour worked by Specialist Inspector            2.86 0.87
Replacement of the above licence if lost £35 £36            2.86 -
Part 4                                                       
Licence to keep petroleum spirit of a quantity —                                                       
- not exceeding 2,500 litres £38 for each year of licence £39 for each year of licence            2.63           
- exceeding 2,500 litres but not exceeding 50,000 litres £53 for each year of licence £54 for each year of licence            1.89           
- exceeding 50,000 litres £108 for each year of licence £111 for each year of licence            2.78           
Transfer of petroleum spirit licence £8 £8            -           
Part 5                                                       
Original approval of premises in which acetylene is to be manufactured or kept £35 plus £115 per hour worked by Specialist Inspector £36 plus £116 per hour worked by Specialist Inspector            2.86 0.87
Amendment of an approval of premises in which acetylene is to be manufactured or kept £35 plus £115 per hour worked by Specialist Inspector £36 plus £116 per hour worked by Specialist Inspector            2.86 0.87
Approval of apparatus in which acetylene is to be manufactured or kept £35 plus £115 per hour worked by Specialist Inspector £36 plus £116 per hour worked by Specialist Inspector            2.86 0.87
Part 6                                                       
Original approval of premises in which acetylene is compressed £35 plus £115 per hour worked by Specialist Inspector £36 plus £116 per hour worked by Specialist Inspector            2.86 0.87
Amendment of an approval of premises in which acetylene is compressed £35 plus £115 per hour worked by Specialist Inspector £36 plus £116 per hour worked by Specialist Inspector            2.86 0.87
Part 7                                                       
Approval of classification of an explosive £60 per hour worked £62 plus £62 per hour worked after the first hour            3.33 -
Part 8                                                       
Testing in connection with specified applications in Parts 3, 5 and 7 Reasonable cost to the Executive of having the testing carried out Reasonable cost to the Executive of having the testing carried out            - -
Part 9

Table 1

                                                                            
Explosives certificate for acquiring and keeping explosives £169            £173                       2.37           
Renewal of the above certificate £138            £142                       2.90           
Explosives certificate for acquiring and keeping explosives for storage of no more than 2000 kg of explosives £179            £184                       2.79           
Renewal of the above certificate £164            £168                       2.44           
Explosives certificate for acquiring and keeping explosives at site for storage of more than 2000 kg of explosives £231            £237                       2.60           
Renewal of the above certificate £205            £210                       2.44           
Replacement of any of the above certificates if lost £31            £32                       3.23           
Table 2                                                                             
Regulation 4(6)(d) check £5            £5                       -           
Schedule 9                                                                             
Applications under Part IX of the Dangerous Substances in Harbour Areas Regulations 1987                                                                             
Grant of an explosives licence or alteration of the terms of an existing explosives licence £624 plus £115 per hour worked £641 plus £116 per hour worked            2.72 0.87
Change of licence name or address £50            £51                       2.00           
Schedule 10                                                                             
Genetically Modified Organisms (Contained Use) Regulations 2000                                                                             
Notification of the intention to use premises for the first time for the purpose of undertaking activities involving genetic modification under regulation 9(1) £465            £465                       0.00           
Notification of an activity involving genetic modification in class 2 under regulation 10(1) £929            £929                       0.00           
Notification of the intention to use premises for the first time for the purpose of undertaking activities involving genetic modification under regulation 9(1) at the same time as notification of an activity involving genetic modification in class 2 under regulation 10(1) £929            £929                       0.00           
Notification of an activity involving genetic modification in class 3 under regulation 11(1) £1,007            £1,007                       0.00           
Notification of the intention to use premises for the first time for the purpose of undertaking activities involving genetic modification under regulation 9(1) at the same time as notification of an activity involving genetic modification in class 3 under regulation 11(1) £1,007            £1,007                       0.00           
Notification of an activity involving genetic modification in class 4 under regulation 11(1) £1,161            £1,161                       0.00           
Notification of the intention to use premises for the first time for the purpose of undertaking activities involving genetic modification under regulation 9(1) at the same time as notification of an activity involving genetic modification in class 4 under regulation 11(1) £1,161            £1,161                       0.00           
Notification of an activity involving genetic modification or organisms other than micro-organisms under regulation 12(1) £929            £929                       0.00           
Notification of the intention to use premises for the first time for the purpose of undertaking genetic modification under regulation 9(1) at the same time as notification of an activity involving genetic modification of organisms other than micro-organisms under regulation 12(1) £929            £929                       0.00           
Notification of an additional information under regulation 15(3) £696            £696                       0.00           
Application for the written agreement of the competent authority under regulation 18(2) where the application is made after a notification has been submitted pursuant to regulation 9(1), 10(1), 11(1) or 12(1) £696 £696            0.00           
Schedule 11                                                                             
Notification of New Substances Regulations 1993                                                                             
Table 1                                                                             
For the evaluation of a notification under regulation 4 ("base set") £4,987            £4,987                       0.00           
For the evaluation of a notification of a substance already notified £2,374            £2,374                       0.00           
For the evaluation of a notification under regulation 5(1)(a) (>10 tonnes per year) £2,619            £2,619                       0.00           
For the evaluation of a notification under regulation 5(1)(b) (>100 tonnes per year) £5,154            £5,154                       0.00           
For the evaluation of a notification under regulation 5(1)(c) (> 1,000 tonnes per year) £3,613            £3,613                       0.00           
For a notification under regulation 6 —                                                                             
(a) quantity of the new substance equal to or more than 100 kg (regulation 6(1)) £1,614            £1,614                       0.00           
(b) quantity of the new substance up to 100 kg (regulation 6(2)) £1,014            £1,014                       0.00           
Evaluation of a notification (whether made under regulation 6(1) or 6(2), as the case may be) in respect of an RTP polymer of an amount equal to or more that 10kg per annum but less than one tonne per annum or the total amount is equal to or more than 500kg but less than 5 tonnes £1,614            £1,614                       0.00           
For an evaluation of information provided under regulation 6(4) (d) (i) in respect of a substance for the purposes of process orientated research and development £646            £646                       0.00           
For an application made by a notifier for an exemption relating to him under regulation 23 £2,619            £2,619                       0.00           
Table 2                                                                             
Additional fee to the fee above for the evaluation of a notification under regulation 4 where there is no adequate risk assessment £2,393 plus VAT            £2,393 plus VAT                       0.00           
Additional fee to the fee above for the evaluation of a notification under regulation 6 where there is no adequate risk assessment                                                                             
(a) quantity of the new substance equal to or more than 100 kg (regulation 6(1)) £578 plus VAT            £578 plus VAT                       0.00           
(b) quantity of the new substance up to 100 kg (regulation 6(2)) £578 plus VAT £578 plus VAT            0.00               
Schedule 12                                                       
Offshore installations Sum of the costs reasonably incurred by the Executive for the function performed Sum of the costs reasonably incurred by the Executive for the function performed            -           
Schedule 13                                                       
Gas safety functions Sum of the costs reasonably incurred by the Executive for the function performed Sum of the costs reasonably incurred by the Executive for the function performed       &