Statutory Instrument 1999 No. 2724

      The M60 Motorway (Improvement Between Junctions 5 and 8) Connecting Roads Scheme 1999


      © Crown Copyright 1999

      Statutory Instruments printed from this website are printed under the superintendence and authority of the Controller of HMSO being the Queen's Printer of Acts of Parliament.

      The legislation contained on this web site is subject to Crown Copyright protection. It may be reproduced free of charge provided that it is reproduced accurately and that the source and copyright status of the material is made evident to users.

      It should be noted that the right to reproduce the text of Statutory Instruments does not extend to the Queen's Printer imprints which should be removed from any copies of the Statutory Instrument which are issued or made available to the public. This includes reproduction of the Statutory Instrument on the Internet and on intranet sites. The Royal Arms may be reproduced only where they are an integral part of the original document.

      The text of this Internet version of the Statutory Instrument which is published by the Queen's Printer of Acts of Parliament has been prepared to reflect the text as it was Made. A print version is also available and is published by The Stationery Office Limited as the The M60 Motorway (Improvement Between Junctions 5 and 8) Connecting Roads Scheme 1999 , ISBN 0 11 085328 8. The print version may be purchased by clicking here. Braille copies of this Statutory Instrument can also be purchased at the same price as the print edition by contacting TSO Customer Services on 0870 600 5522 or e-mail:customer.services@tso.co.uk.

      Further information about the publication of legislation on this website can be found by referring to the Frequently Asked Questions.

      To ensure fast access over slow connections, large documents have been segmented into "chunks". Where you see a "continue" button at the bottom of the page of text, this indicates that there is another chunk of text available.


STATUTORY INSTRUMENTS


1999 No. 2724

HIGHWAYS ENGLAND

The M60 Motorway (Improvement Between Junctions 5 and 8) Connecting Roads Scheme 1999

  Made 21st September 1999 
  Coming into force 18th October 1999 

The Secretary of State for the Environment, Transport and the Regions makes this Scheme in exercise of powers conferred by sections 16, 17, 19 and 106 of the Highways Act 1980[1] and now vested in him[2], and of all other powers enabling him in that behalf: - 

     1. This Scheme may be cited as the M60 Motorway (Improvement Between Junctions 5 and 8) Connecting Roads Scheme 1999, and shall come into force on 18th October 1999.

    
2. In this Scheme:

    (a) all measurements of distance are measured along the route of the relevant highway or, as the case may be, to the soffit of the relevant bridge;

    (b)

      (i) "connecting road" means a special road along a route described in Schedule 1 to this Scheme;

      (ii) "the Motorway" means the M60 Motorway;

      (iii) "the plan" means the plan numbered HA 16/1 CNW 355, marked "The M60 Motorway (Improvement Between Junctions 5 and 8) Connecting Roads Scheme 1999", signed by authority of the Secretary of State for the Environment, Transport and the Regions, and deposited at the Highways Agency, St. Christopher House, Southwark Street, London SE1 0TE; and

      (iv) "the special roads" means each connecting road.

     3. The Secretary of State is authorised to provide the special roads for the exclusive use of traffic of Classes I and II of the classes of traffic set out in Schedule 4 to the Highways Act 1980.

    
4. The centre line of each of the special roads is indicated by a heavy black line on the plan.

    
5. Each of the special roads shall become a trunk road on the date when this Scheme comes into force.

    
6. The Secretary of State is authorised to construct - 



Signed by the Secretary of State for the Environment, Transport and the Regions


Derek Oddy
Divisional Director Highways Agency

21st September 1999



SCHEDULE 1

ROUTES OF THE CONNECTING ROADS


The routes of the connecting roads are as follows:

    (1) Junction with A56 Chester Road at Sale

Two routes to connect the connecting road referred to in paragraph (2) of this Schedule, and given the number 4 on the plan, with the A56 Chester Road (as proposed to be improved by the Secretary of State) at Sale (the special roads along these two routes being given, respectively, the numbers 1 and 2 on the plan);

    (2) Junction with A56 Chester Road and A6144 Old Hall Road at Sale

Two routes to connect the Motorway with the A56 Chester Road and A6144 Old Hall Road (as proposed to be improved by the Secretary of State) at Sale (the special roads along these routes being given, respectively, the numbers 3 and 4 on the plan).



SCHEDULE 2 WITH KEY PLAN AND SITE PLAN

PLANS AND SPECIFICATIONS FOR THE BRIDGE CROSSING THE BRIDGEWATER CANAL AT SALE (BOUNDARY VIADUCT)


Specification
     1. Points of commencement and termination: the bridge commences at a point approximately 210 metres South of Barfoot Bridge over the River Mersey. The bridge terminates at a point approximately 310 metres South of Barfoot Bridge over the River Mersey.

     2. Type of Construction: three span composite steel and reinforced concrete bridge deck supported on in-situ reinforced concrete substructure. Intermediate support columns with crossheads.

     3. Headroom: 4.8 metres above Normal Water Level.



SCHEDULE 3 WITH KEY PLAN AND SITE PLAN

PLANS AND SPECIFICATIONS FOR THE BRIDGE CROSSING THE RIVER MERSEY AT SALE


     1. Points of commencement and termination: the bridge commences at a point approximately 200 metres North-east of Crossford Bridge on the A56, Chester Road. The bridge terminates at a point approximately 270 metres North-east of Crossford Bridge on the A56, Chester Road.

     2. Type of Construction: three span composite steel and reinforced concrete bridge deck supported on in-situ reinforced concrete substructure. Intermediate support columns with crossheads.

     3. Headroom: 12.0 metres above Normal Water Level.



SCHEDULE 4 WITH KEY PLAN AND SITE PLAN

PLANS AND SPECIFICATIONS FOR THE BRIDGE CROSSING THE RIVER MERSEY AT SALE (MERSEY SOUTH BRIDGE)


     1. Points of commencement and termination: the bridge commences at a point approximately 155 metres North-east of Crossford Bridge on the A56, Chester Road. The bridge terminates at a point approximately 170 metres North-east of Crossford Bridge on the A56, Chester Road.

     2. Type of Construction: two span composite steel and reinforced concrete bridge deck supported on in-situ reinforced concrete substructure. Intermediate support column with crosshead.

     3. Headroom: 6.8 metres minimum above Normal Water Level.



SCHEDULE 2: KEY PLAN


SCHEDULE 2: KEY PLAN


SCHEDULE 2: SITE PLAN


SCHEDULE 2: SITE PLAN - Image 1 of 3
SCHEDULE 2: SITE PLAN - Image 2 of 3
SCHEDULE 2: SITE PLAN - Image 3 of 3


SCHEDULES 3 AND 4: KEY PLAN


SCHEDULES 3 AND 4: KEY PLAN


SCHEDULE 3: SITE PLAN


SCHEDULE 3: SITE PLAN - Image 1 of 3
SCHEDULE 3: SITE PLAN - Image 2 of 3
SCHEDULE 3: SITE PLAN - Image 3 of 3


SCHEDULE 4: SITE PLAN


SCHEDULE 4: SITE PLAN - Image 1 of 2
SCHEDULE 4: SITE PLAN - Image 2 of 2


Notes:

[1] 1980 c. 66.back

[2] S.I. 1997/1971.back



ISBN 0 11 085328 8


 

Other UK SIs | Home | National Assembly for Wales Statutory Instruments | Scottish Statutory Instruments | Statutory Rules of Northern Ireland |  Her Majesty's Stationery Office


We welcome your comments on this site
© Crown copyright 1999
Prepared 7 October 1999