The Welsh Highland Railway Order 1999

  1. Introductory Text

  2. PART I PRELIMINARY

    1. 1.Citation and commencement

    2. 2.Interpretation

    3. 3.Incorporation and exclusion of Acts

  3. PART II WORKS PROVISIONS

    1. 4.Power to construct and maintain works

    2. 5.Period for commencement of works

    3. 6.Power to deviate

    4. 7.Power to execute street works

    5. 8.Temporary stopping up of streets

    6. 9.Power to alter layout of streets

    7. 10.Power to keep apparatus in streets

    8. 11.Access to works

    9. 12.Agreements with street authorities

    10. 13.Discharge of water

  4. PART III ACQUISITION AND POSSESSION OF LAND

    1. 14.Power to acquire land

    2. 15.Application of Part I of Act of 1965

    3. 16.Temporary use of land for construction of works

    4. 17.Rights under or over streets

    5. 18.Extinction of rights of way

    6. 19.Time limit for exercise of powers of acquisition

  5. PART IV PROTECTIVE PROVISIONS

    1. 20.Statutory undertakers etc.

    2. 21.For the protection of British Telecommunications PLC

    3. 22.For the protection of Dwŵr Cymru Cyf

    4. 23.For the protection of public electricity suppliers

    5. 24.For the protection of Railtrack PLC

    6. 25.For protection of owners of land adjoining railway

    7. 26.Saving for highway authorities

    8. 27.Public open space

  6. PART V OPERATION OF RAILWAYS

    1. 28.Power to operate and use railways

    2. 29.Maintenance of approved works etc.

    3. 30.Power to charge fares

    4. 31.Removal of obstructions

    5. 32.Traffic control

    6. 33.Power to lop trees overhanging railways

    7. 34.Trespass on railway

    8. 35.Agreement with other railway operators

    9. 36.Level crossings

    10. 37.Accommodation and occupation crossings

  7. PART VI MISCELLANEOUS AND GENERAL

    1. 38.Certification of plans etc.

    2. 39.Service of notices

    3. 40.Borrowing

    4. 41.No double recovery

    5. 42.Arbitration

  8. Signature

  9. SCHEDULES

    1. SCHEDULE 1

      SCHEDULED WORKS

    2. SCHEDULE 2

      STREETS SUBJECT TO STREET WORKS

    3. SCHEDULE 3

      PROVISIONS RELATING TO STATUTORY UNDERTAKERS ETC.

      1. 1.Apparatus of statutory undertakers etc. on land acquired

      2. 2.In the provisions of the Act of 1990, as applied...

      3. 3.Where any apparatus of public utility undertakers or of a...

      4. 4.Paragraph 3 above shall not apply in the case of...

      5. 5.The provisions of the Act of 1990 mentioned in paragraph...

      6. 6.In this Schedule— “the Act of 1990” means the Town...

    4. SCHEDULE 4

      STREETS TO BE TEMPORARILY STOPPED UP

    5. SCHEDULE 5

      MODIFICATION OF COMPENSATION AND COMPULSORY PUR CHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

      1. Compensation enactments

        1. 1.The enactments for the time being in force with respect...

        2. 2.(1) Without prejudice to the generality of paragraph 1 above,...

      2. Adaptation of the Act of 1965

        1. 3.(1) The Act of 1965 shall have effect with the...

        2. 4.For section 7 of the Act of 1965 (measure of...

        3. 5.For section 8 of the Act of 1965 (which relates...

        4. 6.The following provisions of the Act of 1965 (which state...

        5. 7.Section 11 of the Act of 1965 (powers of entry)...

        6. 8.Section 20 of the Act of 1965 (protection for interests...

        7. 9.Section 22 of the Act of 1965 (protection of acquiring...

    6. SCHEDULE 6

      LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN OR USE MADE

  10. Explanatory Note