The Construction Contracts (Northern Ireland) Order 1997 © Crown Copyright 1997 Statutory Instruments printed from this website are printed under the superintendence and authority of the Controller of HMSO being the Queen's Printer of Acts of Parliament. The legislation contained on this web site is subject to Crown Copyright protection. It may be reproduced free of charge provided that it is reproduced accurately and that the source and copyright status of the material is made evident to users. It should be noted that the right to reproduce the text of Statutory Instruments does not extend to the Queen's Printer imprints which should be removed from any copies of the Statutory Instrument which are issued or made available to the public. This includes reproduction of the Statutory Instrument on the Internet and on intranet sites. The Royal Arms may be reproduced only where they are an integral part of the original document. The text of this Internet version of the Statutory Instrument which is published by the Queen's Printer of Acts of Parliament has been prepared to reflect the text as it was Made. A print version is also available and is published by The Stationery Office Limited as the The Construction Contracts (Northern Ireland) Order 1997 , ISBN 0 11 063887 5. The print version may be purchased by clicking here. Braille copies of this Statutory Instrument can also be purchased at the same price as the print edition by contacting TSO Customer Services on 0870 600 5522 or e-mail:customer.services@tso.co.uk. Further information about the publication of legislation on this website can be found by referring to the Frequently Asked Questions. To ensure fast access over slow connections, large documents have been segmented into "chunks". Where you see a "continue" button at the bottom of the page of text, this indicates that there is another chunk of text available.
Whereas this Order is made only for purposes corresponding to those of Part II of the Housing Grants, Construction and Regeneration Act 1996: Now, therefore, Her Majesty, in exercise of the powers conferred by paragraph 1 of Schedule 1 to the Northern Ireland Act 1974 (as modified by section 149 of the said Act of 1996) and of all other powers enabling Her in that behalf, is pleased, by and with the advice of Her Privy Council, to order, and it is hereby ordered, as follows: - Title and commencement 1. - (1) This Order may be cited as the Construction Contracts (Northern Ireland) Order 1997. (2) This Order shall come into operation on such day as the Head of the Department may by order appoint. Interpretation 2. - (1) The Interpretation Act (Northern Ireland) 1954 shall apply to Article 1 and the following provisions of this Order as it applies to a Measure of the Northern Ireland Assembly. (2) In this Order -
Construction contracts.
(b) arranging for the carrying out of construction operations by others, whether under sub-contract to him or otherwise; (c) providing his own labour, or the labour of others, for the carrying out of construction operations.
(2) References in this Order to a construction contract include an agreement -
(b) to provide advice on building, engineering, interior or exterior decoration or on the laying-out of landscape,
in relation to construction operations.
(6) This Order applies only to construction contracts which -
(b) relate to the carrying out of construction operations in Northern Ireland.
(7) This Order applies whether or not the law of Northern Ireland is otherwise the applicable law in relation to the contract.
(b) construction, alteration, repair, maintenance, extension, demolition or dismantling of any works forming, or to form, part of the land, including (without prejudice to the foregoing) walls, roadworks, power-lines, telecommunication apparatus, aircraft runways, docks and harbours, railways, inland waterways, pipe-lines, reservoirs, water-mains, wells, sewers, industrial plant and installations for purposes of land drainage, coast protection or defence; (c) installation in any building or structure of fittings forming part of the land, including (without prejudice to the foregoing) systems of heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, or security or communications systems; (d) external or internal cleaning of buildings and structures, so far as carried out in the course of their construction, alteration, repair, extension or restoration; (e) operations which form an integral part of, or are preparatory to, or are for rendering complete, such operations as are previously described in this paragraph, including site clearance, earth-moving, excavation, tunnelling and boring, laying of foundations, erection, maintenance or dismantling of scaffolding, site restoration, landscaping and the provision of roadways and other access works; (f) painting or decorating the internal or external surfaces of any building or structure.
(2) The following operations are not construction operations within the meaning of this Order -
(b) extraction (whether by underground or surface working) of minerals; tunnelling or boring, or construction of underground works, for this purpose; (c) assembly, installation or demolition of plant or machinery, or erection or demolition of steelwork for the purposes of supporting or providing access to plant or machinery, on a site where the primary activity is -
(ii) the production, transmission, processing or bulk storage (other than warehousing) of chemicals, pharmaceuticals, oil, gas, steel or food and drink;
(d) manufacture or delivery to site of -
(ii) materials, plant or machinery, or (iii) components for systems of heating, lighting, air-conditioning, ventilation, power supply, drainage, sanitation, water supply or fire protection, or for security or communications systems,
except under a contract which also provides for their installation;
(3) The Department may by order add to, amend or repeal any of the provisions of paragraph (1) or (2) as to the operations and work to be treated as construction operations for the purposes of this Order.
(b) to any other description of construction contract excluded from the operation of this Order by order of the Department.
(2) A construction contract with a residential occupier means a construction contract which principally relates to operations on a dwelling which one of the parties to the contract occupies, or intends to occupy, as his residence.
(3) The Department may by order amend paragraph (2).
(2) There is an agreement in writing -
(b) if the agreement is made by exchange of communications in writing, or (c) if the agreement is evidenced in writing.
(3) Where parties agree otherwise than in writing by reference to terms which are in writing, they make an agreement in writing. Right to refer disputes to adjudication 7. - (1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this Article.
(2) The contract shall -
(b) provide a timetable with the object of securing the appointment of the adjudicator and referral of the dispute to him within 7 days of such notice; (c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred; (d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred; (e) impose a duty on the adjudicator to act impartially; and (f) enable the adjudicator to take the initiative in ascertaining the facts and the law.
(3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement.
(4) The contract shall also provide that the adjudicator is not liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omission is in bad faith, and that any employee or agent of the adjudicator is similarly protected from liability. Entitlement to stage payments 8. - (1) A party to a construction contract is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract unless -
(b) it is agreed between the parties that the duration of the work is estimated to be less than 45 days.
(2) The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.
(b) provide for a final date for payment in relation to any sum which becomes due.
(2) Every construction contract shall provide for the giving of notice by a party not later than S days after the date on which a payment becomes due from him under the contract, or would have become due if -
(b) no set-off or abatement was permitted by reference to any sum claimed to be due under one or more other contracts,
specifying the amount (if any) of the payment made or proposed to be made, and the basis on which that amount was calculated.
(2) To be effective such a notice must specify -
(b) if there is more than one ground, each ground and the amount attributable to it,
and must be given not later than the prescribed period before the final date for payment.
(4) Where an effective notice of intention to withhold payment is given, but on the matter being referred to adjudication it is decided that the whole or part of the amount should be paid, the decision shall be construed as requiring payment not later than -
(b) the date which apart from the notice would have been the final date for payment,
whichever is the later.
Prohibition of conditional payment provisions
(b) on the appointment of an administrative receiver or a receiver or manager of its property under Part IV of that Order, (c) on the passing of a resolution for voluntary winding-up without a declaration of solvency under Article 75 of that Order, or (d) on the making of a winding-up order under Part V or Part VI of that Order.
(3) For the purposes of this Article a partnership becomes insolvent on the making of a winding-up order against it under any provision of the Insolvency (Northern Ireland) Order 1989 as applied by an order under Article 364 of that Order.
The Scheme for Construction Contracts in Northern Ireland 13. - (1) The Department shall by regulations make a scheme ("the Scheme for Construction Contracts in Northern Ireland") containing provision about the matters referred to in the preceding provisions of this Order. (2) Before making any regulations under this Article the Department shall consult such persons as it thinks fit. (3) Where any provisions of the Scheme apply by virtue of this Order in default of contractual provision agreed by the parties, they have effect as implied terms of the contract concerned. Service of notices, &c. 14. - (1) The parties are free to agree on the manner of service of any notice or other document required or authorised to be served in pursuance of the construction contract or for any of the purposes of this Order. (2) If or to the extent that there is no such agreement the following provisions apply. (3) A notice or other document may be served on a person by any effective means. (4) Section 24 of the Interpretation Act (Northern Ireland) 1954 (service of documents), as it applies to the service by post of such a notice or other document, shall have effect with the omission of the word "registering" in subsection (1). (5) This Article does not apply to the service of documents for the purposes of legal proceedings, for which provision is made by rules of court. (6) References in this Order to a notice or other document include any form of communication in writing and references to service shall be construed accordingly. Crown application 15. This Order applies to a construction contract entered into by or on behalf of the Crown otherwise than by or on behalf of Her Majesty in her private capacity. Orders and regulations 16. - (1) Orders and regulations under this Order may contain such incidental, supplementary or transitional provisions and savings as the Department considers appropriate. (2) Subject to paragraph (3), orders and regulations made under this Order shall be subject to affirmative resolution. (3) Paragraph (2) does not apply to an order made under Article 1(2). N.H. Nicholls Clerk of the Privy Council (This note is not part of the Order) This Order is made only for purposes corresponding to those of Part II of the Housing Grants, Construction and Regeneration Act 1996. The Order gives any party to a construction contract in Northern Ireland a right to refer disputes to a quick, impartial and investigative adjudication procedure. If no adequate procedure is agreed in the contract, one set out in a scheme made by the Department of the Environment will apply (Article 7). The Order also -
(b) requires construction contracts to provide a mechanism for determining the amount of payments and set a final date for payment of sums due (Article 9); (c) obliges a payer to give a contractor notice with reasons, before the final date of payment, if he intends to withhold payment (Article 10); and (d) makes unenforceable contract provisions which have the effect of making payment dependent upon receipt of payment from a third party, unless payment is delayed because a third party has become insolvent (Article 12).
|
| Other UK SIs | Home | National Assembly for Wales Statutory Instruments | Scottish Statutory Instruments | Statutory Rules of Northern Ireland | Her Majesty's Stationery Office | ||
| We welcome your comments on this site | © Crown copyright 1997 | Prepared 18 June 1997 |