Office of Public Sector Information

Office of Public Sector Information

Main menu and contents

Supplementary menus and contents

Royal arms

Explanatory Notes

Glasgow Airport Rail Link Act 2007

2007 asp 1

Contents

  1. Introduction

  2. The Act

  3. Recipients of the Powers

  4. Relationship With Planning and Railways Regulation

  5. The Act and Related Documents

  6. Structure of the Act

  7. Commentary on Sections

    1. Part 1 – Works

      1. Section 1 – Authority to construct works

      2. Section 2 – The scheduled works

      3. Section 3 – The ancillary works

      4. Section 4 – Permitted deviation within limits

      5. Section 5 – Access to works

      6. Section 6 – Construction and maintenance of altered roads

      7. Section 7 –Works treated as major works for road purposes

      8. Section 8 – Agreements with roads authorities

      9. Section 9 – Temporary stopping up, alteration or diversion of roads

      10. Section 10 – Discharge of water

      11. Section 11 – Safeguarding works to buildings

    2. Part 2 – Land

      1. Introduction

      2. Other compulsory purchase legislation

      3. Compulsory purchase procedures

      4. Compensation

        1. Section 12 – Authority to acquire land

        2. Section 13 – Acquisition of subsoil, airspace or rights

        3. Section 14 – Purchase of specific new rights under land

        4. Section 15 – Rights in roads

        5. Section 16 – Temporary use of land for construction of works

        6. Section 17 – Disregard of certain interests and improvements

        7. Section 18 – Set-off of betterment against compensation

        8. Section 19 – Application of legislation relating to certificates of appropriate alternative Development

        9. Section 20 – No double recovery

        10. Section 21 – Acquisition of part of certain properties

        11. Section 22 – Extinction or suspension of private rights of way

        12. Section 23 – Power to enter land for survey, etc.

        13. Section 24 – Further powers of entry

        14. Section 25 – Persons under disability may grant servitudes, etc.

        15. Section 26 – Period for compulsory acquisition of land

        16. Section 27 – Extension of time

        17. Section 28 – Time limit on validity of notice to treat

        18. Section 29 – Parliamentary plans and book of reference: adjustments agreed with landowners and correction of errors

        19. Section 30 – Restrictions on compulsory purchase in respect of operational airport land

        20. Section 31 – Protection of Access at St James’ Park

    3. Part 3 – Miscellaneous and general

      1. Section 32 – Power to fell, etc. trees or shrubs

      2. Section 33 – Powers of disposal, agreements for operation, etc.

      3. Section 34 – Statutory undertakers, etc.

      4. Section 35 – Arbitration

      5. Section 36 – Service of notices, etc.

      6. Section 37 – Listed buildings

      7. Section 38 – Saving for Town and Country Planning

      8. Section 39 – Blighted land

      9. Section 40 – Method of vesting land

      10. Section 41 – Certification of plans, etc.

      11. Section 42 – Registration of new rights

      12. Section 43 – Mitigation of environmental impacts

      13. Section 44 – Application of Crichel Down Rules

      14. Section 45 – Compliance with code of construction practice and noise and vibration policy

      15. Section 46 – Regulation of mitigation measures

    4. Part 4 – Supplementary

      1. Section 47 – Incorporation of enactments

      2. Section 48 – Application of original railway enactments

      3. Section 49 – Disapplication of statutory and other restrictions on acquisition and use of certain land

      4. Section 50 – Rights of Crown and Scottish Ministers

      5. Section 52 – Short title

  8. Parliamentary History

Introduction

1.These Explanatory Notes have been prepared by John Kennedy & Co., Parliamentary

Agents, on behalf of the promoter Strathclyde Partnership for Transport (“SPT”) in order to assist the reader of the Glasgow Airport Rail Link Act 2007 and to help inform debate on it. They do not form part of the Act and have not been endorsed by the Parliament.

2.The Notes should be read in conjunction with the Act They are not, and are not meant to be, a comprehensive description of the Act. So where a section or schedule, or a part of a section or schedule, does not seem to require any explanation or comment, none is given.

The Act

3.The Act will grant powers to SPT and its successors (for an explanation of successors to SPT see paragraph 7). In the Act the body exercising the powers is called “the authorised undertaker”. The Act will enable the authorised undertaker to build new railway works. All the other powers in the Act, including the other works described below, are required in connection with the construction of the new railway works. In particular, the Act grants compulsory purchase powers. This will ensure that the authorised undertaker will be able to acquire the land or rights in land that are required for the works to be constructed and operated. Paragraphs 4 to 6 below outline the purpose of the Act in greater detail.

4.The principal purpose of the Act is to give statutory authority to SPT and its successors (in the Act called “the authorised undertaker”) for the construction of works to provide a new railway service between Glasgow Airport and Glasgow Central Station. The works comprise:

  • the construction of a new railway spur from a new elevated station at Glasgow

Airport, passing on viaduct over the M8 motorway, across St James’ Park and the

Murray Industrial Area and joining with the existing railway east of Paisley St James Station; and works to the existing railway including the remodelling of Wallneuk Junction east of Paisley Gilmour Street Station; additional track between Arkleston Junction and Shields Junction and at Elderslie; and additional track and new platform at Glasgow Central Station.

5.In connection with these principal works the Act also provides for the alteration of a length of Murray Street and the construction of a new access road leading off the slip road to the M8 at Glasgow Airport. Diversions will be provided. In addition, the Act enables the authorised undertaker to construct miscellaneous works and do other things within the limits of deviation and limits of land to be acquired or used (see paragraph 26 and 65 for explanation) that are required in connection with or in consequence of the railway works including the provision of replacement aviation fuel farm facilities at Glasgow Airport. In the Act the works that will enable these miscellaneous things to be done are called “the ancillary works”.

6.Provision is also included for the compulsory acquisition of land for the scheme.

Recipients of the Powers

7.The powers of the Act will be conferred initially on SPT. Provision is made for SPT to transfer the railway undertaking and related powers in whole or in part, and to share or delegate any of the powers of the Act under section 33 of the Act.

Relationship With Planning and Railways Regulation

8.The development authorised by the Act will be permitted development(1), so that the Act will effectively grant planning permission. The Act restricts this planning permission so that it applies only to works authorised by the Act where construction has been started within 10 years of the Act receiving Royal Assent. The position is described further in the explanation of section 38 (see paragraphs 185 to 189 below).

9.The Act does not state that the authorised undertaker may operate the railway and related facilities. This is because statutory authority to operate the railway will be conferred in another way. Under section 6 of the Railways Act 1993 (c.43) the operation (including maintenance) of a railway asset (which includes track and other infrastructure and stations) requires a licence under section 8 of that Act, and section 122 of the Act confers the benefits of statutory authority on a licensed operator. Statutory authority to operate the railway will also result from the incorporation of the Railways Clauses Consolidation (Scotland) Act of 1845 (c.33). (The incorporation of this and other Acts is explained in paragraphs 15 to 18 and 63 and 207 below.)

The Act and Related Documents

10.The Act is the only document that is enacted by the Parliament. However, although it is free-standing from its accompanying documents, it must be read by reference to the documents referred to in it, namely the Parliamentary plans, the Parliamentary sections and the book of reference. The Parliamentary plans show the lands to be used, the works and facilities to be constructed and (in some cases) the uses to be made of certain areas. The Parliamentary sections show sections of the railway works, including associated road works. The book of reference lists the owners, lessees and occupiers of all lands which may be compulsorily acquired or used or who have interests in any land or water in or over which rights would be extinguished, or interests in the rights that would be extinguished.

11.European legislation on environmental assessment (EC Directive 85/337/EEC as amended by EC Directive 97/11/EC) applies to the Act. The requirements are transposed into domestic law for development projects authorised under planning legislation through the Environmental Impact Assessment (Scotland) Regulations 1999 (SSI 1999/1) as amended by the Environmental Impact Assessment (Scotland) Regulations 2002 (SSI 2002/324).

Structure of the Act

12.Before commenting on the individual sections it may be helpful to explain how the Act operates.

13.Part 1 confers the powers relating to the works themselves. It distinguishes between –

  • those works that are specifically described (the scheduled works described in

  • schedule 1); and

  • works carried out under general powers (the ancillary works as described in schedule 2).

14.Part 2 confers statutory authority for the compulsory purchase of the land required for the scheme. All the sections in this Part are concerned with the implementation of the compulsory purchase powers, so that the Act will have the same effect as would a compulsory purchase order in other types of scheme e.g. for roads.

15.Fairness demands that compulsory purchase under the Act must be on the same standardised basis as any other compulsory purchase in Scotland. Departure from what is generally applicable also has human rights implications. This means that in the Act compulsory purchase must be subject to all the same procedural rules, safeguards and requirements regarding compensation as apply generally. All these provisions are in a large and complex body of law contained in several public Acts of Parliament and case law(2). So that those affected by the Act are on the same footing as those affected by compulsory purchase orders, this body of legislation must be applied to the Act.

16.In theory this might be done either by writing the relevant provisions at length in the Act or by applying the existing public Acts as if they had been included in the Act. Section 47 of the

Act applies the latter. In this it adopts the format for legislation authorising railways and similar infrastructure works which has been in place throughout Great Britain since the mid 19th century and which continues to be utilised(3).

17.The Act follows this precedented format because writing the entire statutory code into the Act is not a practical option. The scheme of the law in question is outlined below in paragraphs 58 to 152 and 207 explaining Part 2 of the Act and section 47. The Acts applied by section 47 contain a total of some 400 sections. Not all sections are relevant, but in much of this legislation it is not possible to say with absolute certainty that a particular provision is not going to be relevant. In addition, this legislation is written in 19th century legal English that would be unacceptable today. As a result, it could not be written into the Act at length without being completely rewritten. The result of this would inevitably be that the meaning would be affected. Such an exercise in statute law revision, however desirable, is far outside the scope of any private Act promoter.

18.The Act accordingly incorporates provisions of the Acts referred to in section 47. These Acts were passed for the purpose of being incorporated as standard “clauses”. They only have effect if they are referred to and implemented by some other piece of legislation such as the Act. The effect of the incorporation is that the incorporated provisions become part of the Act. The Acts in question are—

  • the Lands Clauses Acts(4);

  • the Railways Clauses Consolidation (Scotland) Act 1845 (c.33);

  • the Railways Clauses Act 1863 (c.92).

The Act makes a number of adjustments to the incorporated Acts for the purpose of streamlining the 19th century procedures so as to bring them more nearly into line with the more modern legislative improvements that have been made in England and Wales, but not in Scotland(5) and also to allow for the greater flexibility provided for in the Act. Details of the adjustments are explained in the notes below on sections 13, 21, 23, 24 and 25 of the Act.

Commentary on Sections

Part 1 – Works

19.The meaning of “the scheduled works” and “the ancillary works” is explained in paragraphs 22 to 25 below. They are collectively described as “the authorised works” (defined in section 51).

Section 1 – Authority to construct works

20.Section 1 gives the specific statutory authority for the works which are required(6). In the absence of this section the activities permitted by the Act would potentially be liable to challenge in the courts e.g. on the ground that the railway constituted a legal nuisance. Such an action could potentially result in an order preventing the nuisance by stopping the works (called an interdict). The protection of statutory authority is therefore important to the viability of the scheme because it allows the works to be constructed without the threat of legal challenge.

21.Section 2 refers to the scheduled works as being within the limits of deviation shown on the Parliamentary plans. However, the precise position of the works may move (“deviate”) within those limits, in accordance with section 4.

Section 2 – The scheduled works

22.Section 2 gives effect to schedule 1, which contains the detailed descriptions of the works authorised by the Act described in paragraph 4 above.

Section 3 – The ancillary works

23.Section 3 gives effect to schedule 2, which describes the types of works which may be provided in connection with the scheduled works. Works of this nature will only be authorised by the Act if they are necessary or expedient(7) in connection with the construction of the scheduled works, or are required as a consequence of those works being constructed.

24.Schedule 2 catalogues types of works and operations that are normally necessary for the operation of a railway and also mitigation works and works for the protection of neighbouring landowners. The “railway” itself is only the railway track as laid along the route(8). The ancillary items accordingly range from the provision of stations and platforms to operations such as discharging water during construction(9) and moving utility apparatus(10). They also cover the provision of recreational facilities at St James’ Park and replacement fuel farm facilities at Glasgow Airport. The ancillary works will form an essential part of the authorised works (the term “authorised works” is explained in paragraph 19).

25.At this stage the nature of the ancillary works is known but not the precise ancillary works or, in some cases, their positions. However by virtue of sections 3(2) and 3(3) they can only be constructed within “the Act limits” i.e. the limits shown on the plans in which the powers of the Act can be exercised. This term is defined in section 51 of the Act.

Section 4 – Permitted deviation within limits

26.Section 4 allows for a degree of flexibility within the defined limits. It permits movement or variance from the precise lines and sections shown on the Parliamentary plans and sections. In the Act this is described as “deviation”.

27.The Parliamentary plans show the centre lines of the works and also show limits of deviation around those centre lines. Section 2 specifically states that the authorised works are situated within the limits of deviation. The Act will not accordingly permit the construction of those works outside these lateral limits.

28.The Parliamentary sections show the vertical dimensions and situation of the proposed works. The Act authorises the works in accordance with those dimensions and levels, subject to the flexibility permitted by section 4.

29.Section 4 provides that every work as constructed or maintained may deviate laterally within the limits of deviation, and vertically by up to 3 metres upwards and to any extent downwards. This reflects the outline nature of the authorisation being given by the Act. The works are not being authorised in the fine detail which will be formulated at a later stage when the railway is finally designed. The permission to deviate therefore allows for the normal design process.

30.The ability to deviate vertically to any extent downwards that may be necessary or expedient enables the authorised undertaker to construct the works at whatever depth is needed to achieve stability. It also allows for e.g. the undertaking of ground stabilisation works in the event of mine workings or other geological conditions.

Section 5 – Access to works

31.It will be necessary for the authorised undertaker to provide access from existing roads to land to be used for the authorised works. Section 5 will enable the authorised undertaker to facilitate such access by constructing drop kerbs and similar works both at the points shown on the Parliamentary plans and at other points approved by the roads authority. In the absence of this section such works, amounting to an interference with the road, could not be carried out by the authorised undertaker without first obtaining the consent of the roads authority under section 56 of the Roads (Scotland) Act 1984 (c.54).

Section 6 – Construction and maintenance of altered roads

32.In accordance with standard arrangements when a new road is built, section 6 provides for alterations of roads authorised by the Act to be completed to the reasonable satisfaction of the roads authority, and to become maintainable by the roads authority after an initial 12 month maintenance period during which the authorised undertaker remains liable for any maintenance. This is normal practice to allow any defects that emerge once the roads are first commissioned after construction to be remedied at the expense of the authorised undertaker.

Section 7 –Works treated as major works for road purposes

33.Section 7 is intended to ensure that the regime under Part IV of the New Roads and Street Works Act 1991 (c.22) (in the Act referred to as the 1991 Act) for dealing with apparatus of utilities affected by road works will apply to the authorised works. Part IV of the 1991 Act together with the Road Works (Sharing of Costs of Works) (Scotland) Regulations 2003 and the Codes of Practice issued under the 1991 Act provide a regime dealing with the measures (and the costs of these measures) in relation to utilities’ apparatus in streets as a result of types of road works described in the 1991 Act as “major works for road purposes”. This regime includes a process for identifying and agreeing work required, including any necessary diversions of apparatus, and also deals with the costs of these works. It provides for a contribution to be payable by the utilities in respect of work carried out in relation to their apparatus.

34.“Major works for road purposes” under the 1991 Act cover various categories of road works such as reconstruction or widening of roads, or substantial alterations in the level of roads but only if those works are carried out by the roads authority. Since the authorised undertaker will not be the roads authority, the regime under the 1991 Act would not apply to road works carried out under the powers of the Act. Section 7 accordingly provides for such works carried out by the authorised undertaker to be treated as “major works for road purposes” for the purpose of the 1991 Act. It puts the authorised undertaker in the same position as the roads authority would be if it was carrying out these works and ensures that the same regime will apply.

35.Similar provision relating to the equivalent provisions of the 1991 Act in England was included in the Channel Tunnel Rail Link Act 1996 and is commonly included in Orders under the Transport and Works Act 1992.

Section 8 – Agreements with roads authorities

36.Section 8 permits the authorised undertaker to enter into agreements with the roads authorities to carry out any works to existing roads authorised by the Act. The authorised undertaker is also authorised to delegate by agreement its powers to alter or maintain such altered roads. It is necessary to refer to maintenance because under section 6 the authorised undertaker is required to maintain a road which has been altered under the powers of the Act for a period of 12 months, before the roads authority resumes its maintenance responsibilities.

Section 9 – Temporary stopping up, alteration or diversion of roads

37.It will be necessary for the authorised undertaker during construction temporarily to stop up, alter, or divert roads. Precise details of the roads, timing and duration of closures will be developed as the scheme is designed. Subsection (1) will enable such temporary stoppings up by the authorised undertaker provided consent is obtained from the road works authority(11) under subsection (4). By subsection (5) consent could not be unreasonably withheld but could be given subject to conditions. Under subsection (6) disputes as to the reasonableness of any condition would be determined by arbitration unless the parties agree on an alternative form of disputes procedure. (Section 35 provides for the way in which any arbiter is appointed.)

38.In addition to any condition imposed by the road works authority, the authorised undertaker will be obliged by subsection (2) to provide continued pedestrian access to premises(12) abutting on the temporarily stopped up road.

39.Five necessary temporary stoppings up have been identified at this stage as being required at the locations and for the purposes specified in schedule 3. For this reason subsection (3) authorises these temporary closures and, unlike the unspecified closures, subsection (4)(a) requires consultation with the road works authority but not consent.

40.If there is any suspension of a private right of way under this section compensation would be payable under the compensation code applied by the Act (see paragraph 62).

Section 10 – Discharge of water

41.Section 10 ensures that the authorised undertaker can effectively drain its works, both during construction and thereafter. Subsection (1) enables the authorised undertaker to use any available watercourse or any public sewer or drain for drainage purposes. It provides that within the limits of deviation or the limits of land to be acquired or used(13) the authorised undertaker may lay down, take up or alter pipes or make openings into or connections with the watercourse, public sewer or drain.

42.Under subsection (2) water may not be discharged into an artificial watercourse or a public sewer or drain without the consent of the person to whom it belongs (who in the case of a public sewer or drain will be Scottish Water, a private provider who has made an agreement with Scottish Water under section 1(2)(b) of the Sewerage (Scotland) Act 1968 (c.47) (duty of Scottish Water to provide sewerage for their area) or the roads authority), but although consent may be given subject to reasonable terms and conditions, it cannot be unreasonably withheld.

43.Under subsection (3) an opening into a sewer or drain will have to be made in accordance with plans approved by the person to whom the sewer or drain belongs and subject to such supervision as he provides, but plan approval cannot be unreasonably withheld

44.Subsection (4) requires the authorised undertaker to take such steps as are reasonably practicable to secure that water is free from gravel, soil or other solid substances or from oil or matter in suspension. This might include installation of gullies, filter drains or settlement ponds(14) to separate out such matter from clean water before the water is discharged into a stream, watercourse or public sewer or drain. The precise means of separating such matter from clean water will be determined during the design process in consultation with all appropriate people and bodies, including the roads authority and the Scottish Environment Protection Agency, “SEPA”.

45.Subsection (5) provides that any disagreement between the authorised undertaker and a person owning an artificial watercourse or a public drain or sewer shall be resolved by arbitration. (Section 35 provides for the way in which any arbiter is appointed.)

46.Subsection (6) provides for the continued operation of both Part IV of the New Roads and Street Works Act 1991 (c.22) and the Water Environment (Controlled Activities) (Scotland) Regulations 2005 (S.S.I.2005/348) in tandem with this section. Part IV of the New Roads and Street Works Act 1991 contains a detailed code regulating the carrying out of works in roads by utilities and others. As a result of subsection (6), the authorised undertaker will have to comply with all the requirements of Part IV as to the giving of notice of the works, the compliance with directions given by the road works authority, the duty to co-operate with the road works authority and other undertakers, safety measures, and the provisions for the avoidance of danger, delay or obstruction. The Water Environment (Controlled Activities) (Scotland) Regulations 2005 provide the regulatory framework whereby the authorised undertaker’s activities which impact on the water environment will be controlled and under which compliance with the regulatory requirements will be enforced. SEPA is responsible for authorising ‘controlled activities’ under these Regulations.

47.In the absence of section 10 effective drainage of the works would be subject to the risk of legal action for nuisance in respect of discharges, and subject also to successful private negotiation as regards the use of public sewers or drains. The section is intended to ensure that works authorised by the Parliament can be drained without the risk of legal action or failed private negotiations and will also ensure that drainage from these works is subject to the same pollution controls as other railway and road works.

Section 11 – Safeguarding works to buildings

48.The ground conditions along the route may give rise to a need to prevent or remedy damage to buildings caused by the construction, operation or maintenance of the authorised works or conversely to carry out remedial works to a building which might otherwise affect the safe construction or operation of the authorised works. This will call for underpinning, strengthening or other works for the same purposes (all in the Act called “safeguarding works”). The area where there is a possibility of such works being required is the land within the limits of the Act which are shown on the Parliamentary plans.

49.Subsection (1) accordingly enables the authorised undertaker at its own expense to carry out such safeguarding works to any building within the Act limits as the authorised undertaker considers to be necessary or expedient. Safeguarding works may be carried out during construction or at any time during the five years after any part of the authorised works is first opened for public use.

50.The detailed procedure that must be adopted is set out in schedule 4. This allows for the carrying out of preliminary surveys and (except in an emergency) the service of 14 days’ notice prior to entry and carrying out the safeguarding works. A landowner may question the necessity for safeguarding works and require the issue to be referred to arbitration. However there is no right to question the initial entry to carry out preliminary surveys. Without such preliminary survey it would be very difficult to identify whether and to what extent safeguarding works are required, or to determine the extent of any damage which is caused and for which compensation would be payable. A compulsory power of entry is required in order to make the operation of this provision effective.

51.Where damage is caused by safeguarding works, or where safeguarding works prove to be inadequate within five years after the opening of the relevant authorised works, the authorised undertaker must pay compensation.

Part 2 – Land

Introduction

52.Without provision in the Act the authorised undertaker will not have any compulsory purchase powers to acquire land for construction of the railway and associated infrastructure, or to acquire rights in land e.g. for the purpose of re-routeing statutory undertakers’ apparatus. Provisions are therefore required in the Act to confer appropriate compulsory purchase powers.

53.The principal purposes for which compulsory purchase powers are needed are for the acquisition of:

  • land and rights to access land to construct and then maintain the railway;

  • land for pedestrian and vehicular access to premises;

  • land for replacement of fuel farm at Glasgow Airport;

  • land for road alterations; and

  • land for provision of recreational facilities, associated mitigation and landscaping.

The promoters have also identified land which the authorised undertaker will not need to acquire permanently but which will need to be used to allow temporary access or to be occupied temporarily during the construction period e.g. as construction sites. (In the Act temporary occupation is referred to as “temporary possession”.)

54.In many cases (roads and housing are examples) powers are given by compulsory purchase order made by the authority that is to have the powers, or by the relevant Minister. In the present case compulsory purchase is authorised by the Act itself: there will not be a separate compulsory purchase order. The compulsory purchase powers are in Part 2 of the Act, either set out in full or applying the compulsory purchase and compensation law that applies to compulsory purchase orders. This suite of provisions gives the authorised undertaker powers for the compulsory purchase of land and rights over land, access and temporary possession, all of which are needed in connection with the authorised works. It also deals with issues concerning compulsory purchase procedures, entry on land, the assessment of compensation and procedures relating to compensation, as well as the particular issues dealt with in specific sections of the Act. The effect of the provisions is explained in greater detail below.

55.The land affected by the compulsory purchase powers in the Act is the land described – that is, given a description and not merely referred to as an unused plot number – in the book of reference. On the Parliamentary plans it is all the land within the limits of deviation(15) and within the limits of land to be acquired or used(16).

56.The compulsory purchase powers conferred by the Act will enable the authorised undertaker to acquire the land necessary to construct the works authorised by the Act. In the absence of compulsory purchase powers this would not be possible if landowners refused to make their land available. The acquisition of land under compulsory powers (including purchase by agreement but where compulsory purchase powers have been conferred) also operates to extinguish all rights and claims which are inconsistent with the scheme and thus might inhibit the construction of the works. These include private rights of way as well as rights to maintain plant and equipment in the land.

Other compulsory purchase legislation

57.The provisions in the Act simply grant compulsory purchase powers. They do not include the detailed procedures required for implementation. Implementation is governed by an existing body of law relating to the detailed procedure for any compulsory purchase (whether authorised by Act, compulsory purchase order or some other means) and the way in which compensation is determined. This law is all applied to the compulsory purchase powers conferred by the Act(17). An outline of this applied legislation is given below.

Compulsory purchase procedures

58.After the Act has been enacted, the first stage of the procedures will be the service on each landowner whose land is required of a notice (called a notice to treat) under section 17 of the Lands Clauses Consolidation (Scotland) Act 1845 (c.19) (in the Act called “the 1845 Lands Act”). This notice will inform those with an interest in land of the intention of the authorised undertaker to acquire the land or the rights described in the notice. Service of a notice to treat results in the authorised undertaker being in the same position as if a binding contract for the purchase of the land had been completed. As an alternative to serving a notice to treat, the authorised undertaker may acquire land by a general vesting declaration (on this see paragraphs 192 to 196).

59.The authorised undertaker may need to enter land to start the works in advance of completing its purchase. Before it can do so it must serve a notice (called a notice of entry) on the landowner.

60.Where a landowner is unwilling or unable to sell the authorised undertaker may acquire the land by executing a notarial instrument(18). The same procedure applies where the authorised undertaker has made diligent efforts to find the landowner but has been unable to do so. These provisions are intended to ensure that a landowner cannot hold up the scheme unreasonably by refusing to sell and that the scheme can go ahead even if the landowner cannot be traced.

61.In practice an authority having compulsory purchase powers will often be able to buy land by agreement without having to resort to the formal statutory procedures. When this happens the Lands Clauses Acts give powers of sale to landowners (such as trustees) who otherwise might not be at liberty to sell. Although land may be purchased by agreement, the compensation rules will be the same as if the land had been purchased compulsorily.

Compensation

62.The money paid for lands and rights purchased compulsorily is known as compensation. The body of law governing rights to compensation where there are compulsory purchase powers and the rules for calculating the basis and amount of compensation are in part in the common law, in part in the Lands Clauses Acts and in part in Part I of the Land Compensation (Scotland) Act 1963 (c.51). This detailed body of law will apply to compulsory purchase under the Act. Disputes about compensation will be referred to the Lands Tribunal for Scotland(19).

1

“Permitted development” means development which is permitted by article 3 of the Town and Country Planning (General Permitted Development) (Scotland) Order 1992 (SI 1992/223) to be carried out without the need to apply for planning permission. The precise scope of the different classes of permitted development and the conditions subject to which it is permitted are set out in Schedule 1 to the 1992 Order. The relevant class in this case is Class 29 (development authorised by private Act, etc.). Back [1]

2

The relevant law has been described as having “become an unwieldy and lumbering creature” – see ‘Fundamental Review of the Laws and Procedures Relating to Compulsory Purchase and Compensation: Final Report’, Office of the Deputy Prime Minister, January 2003, para. 20. Back [2]

3

Recent Scottish examples of provisions similar to section 47 are the Stirling-Alloa-Kincardine Railway and Linked Improvements Act 2004, section 37, the British Railways (No. 2) Order Confirmation Act 1994 (c.ii), s.3 (authorising an upgrading of the part of the present route between Cambus and Alloa) and the British Railways (No. 3) Order Confirmation Act 1994 (c.iii), s.3 (authorising an upgrading of the railway between Hamilton and Larkhall). More recent examples are in Orders made under the Transport and Works Act 1992, which are the means of authorising most infrastructure works in England and Wales and which apply the equivalent English Law. See for example article 4 of the Leeds Supertram (Extension) Order 2001 SI 2001/1347), articles 4 and 5 of the Leeds Supertram (Land Acquisition and Road Works) Order 2001 (SI 2001/1348) and articles 3 and 10 of the Heathrow Express Railway Extension Order 2002 (SI 2002/1064). Back [3]

4

i.e. The Lands Clauses Consolidation (Scotland) Act 1845 (c.19) and the Lands Clauses Consolidation Acts Amendment Act 1860 (c.106), and any Acts for the time being in force amending those Acts – see The Scotland Act 1998 (Transitory and Transitional Provisions) (Publication and Interpretation etc. of Acts of the Scottish Parliament) Order 1999 (SI 1999/1379), Schedule 1. Where a word or expression is defined in the 1999 Interpretation Order, that definition will apply unless a contrary intention appears in the enactment being interpreted. (Bennion, ‘Statutory Interpretation’ (4th edn. 2002) p. 497.) Where, as with this definition, an Interpretation Order definition is intended to apply, the definition is not repeated in the Act. (“The purpose of an Interpretation Act is by the use of labelling definitions to shorten the language which needs to be used in legislation”. Bennion, p. 491.) Back [4]

5

“… it is unfortunate in view of … the criticism which has been levelled at the [Lands Clauses Consolidation (Scotland) Act 1845] that Parliament has not found time to produce more up-to-date legislation as was done in England with the passing of the Compulsory Purchase Act 1965 (c.56).” Stair Memorial Encyclopaedia, Title ‘Compulsory Acquisition and Compensation’ para. 13. Back [5]

6

The need for such authority is explained in paragraph 12 of the Promoter’s Memorandum. Back [6]

7

i.e. advantageous; suitable, appropriate (Concise Oxford English Dictionary). Back [7]

8

See, by virtue of section 81(3) of the Railways Act 1993 (c.43), the definition of “railway” in section 67(1) of the Transport and Works Act 1992 (c.42). Back [8]

9

e.g. when pumping away water from a site so as to be able to lay track on dry ground. Back [9]

10

e.g. water mains and power supply cables. Back [10]

11

i.e. in the case of a public road, the roads authority for the road, and in the case of any other road the road managers (New Roads and Street Works Act 1991 (c.22), s.108(i)). Back [11]

12

“Premises” is used in its ordinary meaning i.e. places, landholdings (including buildings). Except where it is especially defined, as in some legislation, it is not a technical term. “Premises” is an ordinary word of the English language which takes colour and content from the context in which it is raised … it has, in my opinion, no recognised and established primary meaning.” Maunsell v Olins [1975] 1 All ER 16 at 19, HL, per Viscount Dilhorne. Back [12]

13

For explanation of this expression see paragraph 65 below. Back [13]

14

A “gully” is a concrete box with a pipe and a metal grid on top: solid materials settle on the bottom of the box and water to be discharged continues along the pipe. A “filter drain” (also known as a “French drain”) is a ditch filled with stones which act to remove large solid particles from the water before the water is discharged into the ground or a drainage system. A “settlement pond” is a large pond that allows water to sit while slow settlement of particles takes place. Back [14]

15

For an explanation of “limits of deviation” see notes on section 4. Back [15]

16

i.e. land situated outside the limits of deviation which is required to be acquired or used for specific purposes - see sections 12(b), 13, 14 and 16 and schedules 5 and 6. Back [16]

17

For an explanation of the reason for applying other Acts see paragraphs 15 to 17 above. Back [17]

18

“Notarial instrument”: the term used in sections 74 to 76 of the 1845 Lands Act when referring to the formal document that in these circumstances will vest land in the authorised undertaker. The expression is only a description. There is no special style laid down for this type of deed. Back [18]

19

The Lands Tribunal for Scotland was set up under the Lands Tribunal Act 1949 (c.42). Section 8 of the Land Compensation (Scotland) Act 1963 (c.51) makes the tribunal responsible for determining disputes about compensation for compulsory purchase. The tribunal’s composition is governed by section 2(1) and (9)(b) of the 1949 Act (substituted by section 50(1) of the Conveyancing and Feudal Reform (Scotland) Act 1970 (c.35)). It comprises a President (who must be a suitably qualified lawyer) and such number of other members as is determined by the Lord President of the Court of Session. The other members must be either suitably qualified lawyers or persons with experience in the valuation of land. The President and other members are all appointed by the Lord President (in the case of valuer members after consultation with the Royal Institution of Chartered Surveyors). Back [19]