SCHEDULE 10 Code of construction practice

(introduced by section 46)

1 Before commencing construction of the authorised works located in the area of a local planning authority the authorised undertaker shall secure that there is submitted to that local planning authority for its written approval—

(a) the code of construction practice; and

(b) one or more draft local construction codes relating to so much of the authorised works as is situated in the area of the local planning authority concerned.

2 The local planning authority shall send a copy of every code submitted pursuant to paragraph 1, and any amendment or replacement proposed by the authorised undertaker pursuant to paragraph 3, to SNH and SEPA and shall take account of any representations made to the local planning authority by either of those bodies.

3 The authorised undertaker may with the approval of the local planning authority (and shall if so required by the local planning authority) amend or replace the code of construction practice or any local construction code.

4 The provisions of the code of construction practice and any local construction code, as from time to time amended or replaced shall have effect as conditions to which section 48 applies.

SCHEDULE 11 Works affecting the River Tweed Special Area of Conservation

(introduced by section 47)

Part 1 Works requiring special measures

1 This Part of this schedule applies to the sites specified in the table.

Location ID No. Description Co-ordinates
(1) (2) X Y
(3)
4 Confluence of Gala Water and Shoestanes Barn 340406 654396
5 Underbridge 49, near Heriot 340406 654396
6 Proposed river diversion (part of Work No. 5D) 340512 654217
7 Replacement culvert near Shoestanes (part of Work No. 5) 340509 654093
8 River bank, near Heriot Station 340570 653982
9 River bank protection, near Stagebank 341113 653144
10 Underbridge 52, near Little Gala 341542 652594
11 River bank protection, near Haltree 341845 652269
13 Underbridge 53, near Crookstone Mill 342456 651192
14 Underbridge 54, Hollowsbank 342373 650850
15 Underbridge 55, Hollowsbank 342346 650768
16 Underbridge 56, near Bower 342352 650341
17 Underbridge 58, Fountainhall 342992 649536
18 Riverbank protection, near Burnhouse 343487 649126
19 Underbridge 60, Plenploth North 344152 648785
20 Underbridge 61, Torquhan South 344300 647927
22 Riverbank protection, Pirnhouse 344469 647167
23 Underbridge 64, Watherston Culvert 344325 646697
24 Riverbank protection, Craigsbank 344303 646495
25 Underbridge 65, Watherston Bridge 344166 646031
26 Underbridge 67, Gala Bank 344308 645582
27 Riverbank protection, Millbank, Section 1 344699 645369
28 Riverbank protection, Millbank, Section 2 345158 645175
29 Riverbank protection, Lady’s Park, near Stow 345420 643931
30 Underbridge 70, Luggate Bridge 345265 643137
31 Underbridge 72, Ferniehurst Water 344790 641965
32 Underbridge 73B, between Bowshank Farm and Gala Water 345187 641416
33 Underbridge 74, Bowshank North 345230 641382
34 Underbridge 77, Bowshank South 345419 641059
35 Riverbank protection, Bowshank South 345384 640816
36 Underbridge 78, Bowshank South 345417 640794
37 Riverbank protection, Bowland 345599 640064
38 Riverbank protection, Whitelee House 346533 639191
39 Underbridge 83, Whitelee Culvert 346668 639144
40 Underbridge 84, Whinwater 347089 638912
41 Riverbank protection, Gala Water at Torwoodlee 347292 638846
42 Underbridge 87, Torwoodlee Water 347505 637885
43 Underbridge 88, Torwoodlee Culvert 347501 637865
45 Underbridge 92, Ryehaugh Water 347568 637496
46 Underbridge 95, Kilnknowe 348260 637030
49 Underbridge 104, Red Bridge 351570 635256
50 Underbridge 45, near Heriot 339946 655241
51 Underbridge 47, near Heriot 340284 654752
52 Underbridge 48, near Heriot 340366 554513

2 The authorised undertaker shall not undertake any works for the protection of river banks at sites ID8, ID9, ID11, ID22, ID24, ID27, ID28, ID29, or ID37.

3 The location of any work for the protection of river banks to be undertaken by the authorised undertaker at sites ID4, ID18, ID35, ID36, ID38, ID41, ID42 and ID43 shall be approved by SNH.

4 Before commencing the construction of any works, or carrying out any operations, at any of the sites to which this schedule applies, the authorised undertaker shall consult SNH regarding—

(a) detailed engineering design;

(b) construction methods;

(c) pollution control;

(d) timing of works and operations;

(e) conservation of specific habitats or of habitats of specific species,

and shall implement such detailed mitigation measures regarding such matters as SNH may require.

5 The authorised undertaker shall secure that the code of construction practice is amended from time to time as appropriate so as to procure the carrying out of measures required pursuant to paragraph 4.

6 Where and to the extent that any measure required by paragraph 4 cannot be dealt with in the code of construction practice (as from time to time amended or replaced), it shall be specified in an agreement to which the local planning authority and the authorised undertaker are party.

7 Any provision amending the code of construction practice pursuant to paragraph 5, and the provisions of any agreement entered into pursuant to paragraph 6, shall have effect as a condition to which section 48 applies.