PART 2 continued
(1) Subsection (2) applies where a verifier—
(a) grants, or makes an amendment to, a building warrant (other than a warrant for demolition), or
(b) accepts a completion certificate submitted under section 17(4),
in respect of any building.
(2) Where the verifier considers it necessary to do so for securing that the purposes of any provision of building regulations are not frustrated, the verifier must, on granting or making the amendment to the building warrant or, as the case may be, accepting the completion certificate, impose on the owner of the building such continuing requirements (in addition to any imposed by virtue of section 2) in relation to the building as the verifier considers necessary for securing that matter.
(3) Continuing requirements imposed under this section must state the provision of building regulations to which they relate.
(1) A verifier must—
(a) on an application made to it for discharge of a continuing requirement imposed under section 22, discharge the continuing requirement if satisfied that—
(i) the building in relation to which the requirement was imposed complies with building regulations (as they apply at the time of the application), and
(ii) the requirement is no longer necessary for securing that the purposes of the provision of building regulations to which it relates are not frustrated,
(b) on an application made to it for variation of a continuing requirement imposed under that section, make the variation if satisfied that—
(i) the building in relation to which the requirement was imposed complies with building regulations (as they apply at the time of the application), and
(ii) the variation will not result in the purposes of the provision of building regulations to which the requirement relates being frustrated.
(2) References in this Act to continuing requirements imposed under section 22 include such requirements as varied under this section.
(3) Continuing requirements imposed in relation to a building under section 22 cease to have effect if—
(a) a building warrant is granted in respect of the building, or
(b) a completion certificate submitted under section 17(4) in respect of the building is accepted.
(4) Subsection (3) does not affect the power of the verifier to impose further continuing requirements in relation to the building under section 22 on granting the building warrant or, as the case may be, accepting the completion certificate referred to in subsection (3).
(1) Every local authority must keep a register (a “building standards register”) for the area of the authority containing information in relation to—
(a) applications for building warrants and amendments to building warrants,
(b) the manner in which such applications have been dealt with, and
(c) completion certificates and their acceptance or rejection.
(2) The Scottish Ministers may by regulations make provision as to—
(a) matters, in addition to those specified in subsection (1)(a) to (c), in relation to which building standards registers are to contain information,
(b) the information which such registers are to contain,
(c) the form and manner in which such registers are to be kept.
(3) Regulations under subsection (2) may also make provision for—
(a) building standards registers to include copies of plans, specifications, estimates of costs, certificates issued by certifiers and other documents,
(b) the removal from such registers of all or part of entries relating to applications, and things relating to them.
(4) Building standards registers must be kept open for public inspection at all reasonable times.
(1) This section applies where the Scottish Ministers consider that, for any of the purposes of—
(a) securing the health, safety, welfare and convenience of persons in or about buildings and of others who may be affected by buildings or matters connected with buildings,
(b) furthering the conservation of fuel and power, and
(c) furthering the achievement of sustainable development,
buildings of any description to which building regulations apply ought to comply with a provision of the regulations.
(2) Where this section applies, the Scottish Ministers may direct all local authorities, particular local authorities or local authorities of a particular description to secure that such buildings comply with that provision of the regulations.
(3) A local authority must, if required to do so by a direction under subsection (2) and may, in any other case where it appears to the authority that a building of a description specified in such a direction does not comply with a provision of the building regulations specified in the direction in relation to buildings of that description, serve on the owner of the building a notice (a “building regulations compliance notice”)—
(a) specifying the provision of the regulations in question,
(b) requiring the owner to secure, by such date (not less than 28 days after the date on which the notice takes effect) as the notice may specify, that the building complies with that provision,
(c) specifying any particular steps which the authority requires the owner to take for that purpose, and
(d) specifying the date on which the notice is to take effect.
(4) Subject to subsection (8), nothing in this section affects any requirement to obtain a building warrant (where one is required) for work required to comply with a building regulations compliance notice.
(5) Where a local authority serving a building regulations compliance notice is a verifier authorised to exercise functions in relation to the matter in question, the notice may require—
(a) any application for a building warrant for work required to comply with the notice to be made, and
(b) any completion certificate in respect of such work to be submitted,
to the authority.
(6) If, by the date specified under subsection (3)(b) (or such later date as the local authority may have substituted under subsection (9)(b)), the owner has—
(a) applied for a building warrant in respect of any work required to comply with the notice, and
(b) (if the local authority is not the verifier to which the application is made) notified the authority of the making of the application,
the notice has effect with the substitution for the date or later date of such other date (not less than 28 days after the date on which the verifier’s decision on the application takes effect) as the local authority may specify.
(7) If, by the date specified under subsection (3)(b) (or such later date as may have substituted under subsection (6) or (9)(b)), the owner has not complied with the notice—
(a) the owner is guilty of an offence, and
(b) the authority may carry out such work as is necessary to make the building comply with the provision of building regulations specified in the notice and may recover from the owner any expenses reasonably incurred by it in doing so.
(8) A building warrant is not required for the carrying out of work by a local authority under subsection (7)(b) but, after the completion of such work, the local authority must register in the building standards register a completion certificate certifying that the building complies with the provision of building regulations specified in the notice in question.
(9) The local authority may—
(a) withdraw a building regulations compliance notice,
(b) waive or relax any requirement of such a notice, including substituting a later date for the date specified under subsection (3)(b) or (6),
whether or not the notice has taken effect.
(10) The withdrawal of a building regulations compliance notice does not affect the power of the local authority to issue a further such notice.
(1) This section applies where it appears to a local authority that the owner of a building is failing to comply with a continuing requirement imposed on the owner—
(a) by building regulations by virtue of section 2, or
(b) by a verifier under section 22.
(2) Where this section applies, the local authority may serve on the owner of the building a notice (a “continuing requirement enforcement notice”)—
(a) specifying the continuing requirement in question,
(b) requiring the owner to take, by such date (not less than 28 days after the date on which the notice takes effect) as the notice may specify, such steps as the notice may specify for the purpose of complying with the continuing requirement,
(c) specifying the date on which the notice is to take effect.
(3) If, by the date specified under subsection (2)(b) (or such later date as may have been substituted under subsection (5)(b)), the owner has not complied with the notice—
(a) the owner is guilty of an offence, and
(b) the authority may carry out such work as is necessary to comply with the notice and may recover from the owner any expenses reasonably incurred by it in doing so.
(4) After the completion of such work the local authority must register in the building standards register a completion certificate certifying that the work has been completed in accordance with the notice in question.
(5) The local authority may—
(a) withdraw a continuing requirement enforcement notice,
(b) waive or relax any requirement of such a notice, including substituting a later date for the date specified under subsection (2)(b),
whether or not the notice has taken effect.
(6) The withdrawal of a continuing requirement enforcement notice does not affect the power of the local authority to issue a further such notice.
(1) This section applies where it appears to a local authority that—
(a) work in respect of a building for which a building warrant is required under section 8(1)(a) has been or is being carried out—
(i) without a building warrant, or
(ii) where a building warrant has been granted, otherwise than in accordance with the warrant, or
(b) a building is of a description referred to in subsection (1) of section 14 and has not been demolished by the expiry of the period determined under that section for its demolition.
(2) Where this section applies, the local authority may serve on the relevant person a notice (a “building warrant enforcement notice”) requiring that person—
(a) in a case referred to in subsection (1)(a)(i) where the work has been carried out, to submit a completion certificate to a verifier and to secure the verifier’s acceptance of the certificate,
(b) in a case referred to in subsection (1)(a)(i) where the work is being carried out, to obtain a building warrant for the work,
(c) in a case referred to in subsection (1)(a)(ii)—
(i) to secure that the work complies with the warrant, or
(ii) to obtain an amendment to the building warrant in respect of the non-compliance,
(d) in a case referred to in subsection (1)(b), to obtain a building warrant for the demolition of the building and to demolish the building,
by such date (not less than 28 days after the date on which the notice takes effect) as the notice may specify.
(3) In this section, the relevant person, in relation to a building, is—
(a) in a case referred to in subsection (1)(a)—
(i) where the work has been or is being carried out otherwise than on behalf of another person, the person who carried it out or is carrying it out,
(ii) where the work has been or is being carried out by a person on behalf of another person, that other person,
(iii) if the owner of the building does not fall within sub-paragraph (i) or (ii) and the person specified in those sub-paragraphs cannot be found or no longer has an interest in the building, the owner,
(b) in a case referred to in subsection (1)(b), the owner of the building.
(4) Where a local authority serving a building warrant enforcement notice under subsection (2)(a) or (b) is a verifier authorised to exercise functions in relation to the matter in question, the notice may require the completion certificate or, as the case may be, the application for the building warrant to be submitted to the authority.
(5) A building warrant enforcement notice—
(a) must specify the date on which the notice is to take effect,
(b) may specify particular steps which the local authority requires the person on whom the notice is served to take in complying with the notice,
(c) may, in a case referred to in subsection (1)(a) where work is being carried out, require the person on whom the notice is served to suspend work (other than work for complying with the notice) until the notice has been complied with.
(6) If, by the date specified under subsection (2) (or such later date as the local authority may have substituted under subsection (9)(b)), the person on whom the notice is served has—
(a) applied for a direction under section 3 in relation to the building in question, and
(b) notified the authority of the making of the application,
the notice has effect with the substitution for the date or later date of such other date (not less than 28 days after the date on which the decision on the application for the direction takes effect) as the local authority may specify.
(7) If, by the date specified under subsection (2) (or such later date as the local authority may have substituted under subsection (6) or (9)(b)), the person on whom the notice is served has not complied with the notice—
(a) the person is guilty of an offence, and
(b) the authority may carry out the work necessary—
(i) in a case referred to in subsection (2)(a) or (b), to secure that the work complies with building regulations,
(ii) in a case referred to in subsection (2)(c) or (d), to secure compliance with the notice,
and may recover from the person any expenses reasonably incurred by it in doing so.
(8) A building warrant is not required for the carrying out of work by a local authority under subsection (7)(b) but, after the completion of such work, the local authority must register in the building standards register a completion certificate certifying that the work complies with building regulations or, as the case may be, that the work has been completed in accordance with the notice in question.
(9) The local authority may—
(a) withdraw a building warrant enforcement notice,
(b) waive or relax any requirement of such a notice, including substituting a later date for the date specified under subsection (2),
whether or not the notice has taken effect.
(10) The withdrawal of a building warrant enforcement notice does not affect the power of the local authority to issue a further such notice.