(7) The Authorities shall before commencing construction of the relevant works supply to Railtrack PLC proper and sufficient plans for the reasonable approval of the engineer and shall not commence such construction of the relevant works until plans thereof have been approved in writing by the engineer or settled by arbitration:

Provided that the approval of the engineer under this paragraph shall not be unreasonably withheld or delayed and if within 56 days after such plans have been supplied to Railtrack PLC the engineer has not intimated his disapproval thereof and the grounds of his disapproval he shall be deemed to have approved the same:

(8) Upon signifying his approval or disapproval of the plans the engineer may specify any protective works (whether temporary or permanent) which in his opinion should be carried out before the commencement of the relevant works to ensure the safety or stability of railway property, the continuation of safe and efficient operation of the railways of Railtrack or the services of operators using the same (including any relocation of works, apparatus and equipment necessitated by the relevant works) and such protective works as may be reasonably necessary for those purposes shall be constructed by Railtrack or by the Authorities, if Railtrack PLC so desires, with all reasonable dispatch and the Authorities shall not commence the construction of the relevant works until the engineer has notified the Authorities that the protective works have been completed to his reasonable satisfaction:

(9) Blasting operations in connection with the works shall not be carried out except at such times and in such manner as the engineer may approve, which approval shall not be unreasonably withheld:

The relevant works shall, when commenced, be constructed—

(i) with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled as aforesaid;

(ii) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;

(iii) in such manner as to cause as little damage to railway property as may be; and

(iv) so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Railtrack or the traffic thereon, the operation of any railway station and the use by passengers of railway property;

and, if any damage to railway property or any such interference or obstruction is caused or takes place in consequence of the construction of the relevant works, the Authorities shall, notwithstanding any such approval as aforesaid, make good such damage and shall pay to Railtrack PLC all reasonable expenses to which Railtrack may be put and compensation for any loss which Railtrack may sustain by reason of any such damage, interference or obstruction;

(b) Nothing in this paragraph shall impose any liability on the Authorities with respect to any damage, cost, expense or loss which is attributable to the neglect or default of Railtrack or its servants or agents:

(11) The Authorities shall—

(a) at all times afford reasonable facilities to the engineer for access to the relevant works during their construction; and

(b) supply the engineer with all such information as he may reasonably require with regard to the relevant works or the method of construction thereof:

(12) Railtrack shall at all times afford reasonable facilities to the Authorities and their agents for access to any works carried out by Railtrack under this section during their construction and shall supply the Authorities with such information as they may reasonably require with regard to such works or the method of construction thereof:

If any alterations or additions, either permanent or temporary, to railway property are reasonably necessary during the construction of the relevant works or during a period of 12 months after the completion thereof in consequence of the construction of the relevant works, and Railtrack PLC gives to the Authorities reasonable notice of Railtrack’s intention to carry out such alterations or additions, specifying the alterations or additions to be carried out, the Authorities shall pay to Railtrack PLC the reasonable cost thereof including, in respect of permanent alterations and additions, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Railtrack in maintaining, working and, when necessary, renewing any such alterations or additions;

(b) The engineer shall, in respect of the capitalised sums referred to in this paragraph and paragraph (14) (a) below, provide such details of the formula by which those sums have been calculated as the Authorities may reasonably require;

(c) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving shall be set off against any sum payable by the Authorities to Railtrack PLC under this paragraph:

(14) The Authorities shall repay to Railtrack PLC all reasonable fees, costs, charges and expenses reasonably incurred by Railtrack—

(a) in constructing any protective works under the provisions of paragraph (8) above including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;

(b) in respect of the employment of any inspectors, signalmen, watchmen and other persons whom it is reasonably necessary to appoint for inspecting, watching, lighting and signalling railway property and for preventing as far as may be reasonably practicable interference, obstruction, danger or accident arising from the construction, maintenance, or failure of the relevant works;

(c) in respect of any special traffic working resulting from any speed restrictions which are necessary as a result of the construction, maintenance, or failure of the relevant works and which may in the opinion of the engineer be required to be imposed or from the substitution, suspension or diversion of services which may be reasonably necessary for the same reason;

(d) in respect of any additional temporary lighting of railway property in the vicinity of the relevant works being lighting made reasonably necessary as a result of the relevant works or the failure thereof;

(e) in respect of the approval by the engineer of plans submitted by the Authorities and the supervision by him of the construction of the relevant works:

(15) If at any time after the completion of the relevant works Railtrack PLC gives notice to the Authorities informing them that the state of maintenance of the relevant works appears to be such as adversely affects the operation of railway property, the Authorities shall, on receipt of such notice, take such steps as may be reasonably necessary to put the relevant works in such state of maintenance as not adversely to affect railway property:

(16) All temporary structures, erections, works, apparatus and appliances erected or placed by the Authorities under the powers of this Act or the Act of 1957 upon, over or under any railway of Railtrack shall, as soon as reasonably practicable, be removed by the Authorities at times to be agreed with, and to the reasonable satisfaction of, the engineer and in such a way as to cause as little damage to railway property and as little interference with or delay or interruption to, the traffic on the railways of Railtrack as may be; and if any damage to railway property or such interference, delay or interruption is caused by any such failure to remove any such temporary structures, erections, works, apparatus or appliances, the Authorities shall forthwith make good such damage and pay to Railtrack PLC the reasonable costs and expenses to which Railtrack may be put and reasonable compensation for any loss which Railtrack may sustain by reason of such damage, interference, delay and interruption:

(17) Before providing any illumination or illuminated traffic sign on or in connection with the relevant works the Authorities shall consult with Railtrack PLC and comply, save as otherwise directed by the Secretary of State or the Corporation of Trinity House of Deptford Strond, with its reasonable requirements in regard thereto with a view to ensuring that such illumination or illuminated sign could not be confused with any railway signal or other light for controlling, directing or securing the safety of traffic on the railway:

(18) Any additional expenses which Railtrack may reasonably incur after giving 56 days' notice to the Authorities in altering, reconstructing or maintaining railway property under any powers existing at the passing of this Act by reason of the existence of the relevant works shall be repaid by the Authorities to Railtrack PLC:

The Authorities shall be responsible for and make good to Railtrack PLC all reasonable costs, charges, damages and expenses not otherwise provided for in this section which may be occasioned to, or reasonably incurred by, Railtrack—

(i) by reason of the construction or maintenance of the relevant works or the failure thereof; or

(ii) by reason of any act or omission of the Authorities or of any person in their employ or of their contractors or others whilst engaged upon the relevant works;

and the Authorities shall indemnify Railtrack from and against all claims and demands arising out of or in connection with the relevant works or any such failure, act or omission as aforesaid and the fact that any act or thing may have been done in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under his supervision shall not (if it was not attributable to the neglect or default of Railtrack or of any person in its employ or of its contractors or agents) excuse the Authorities from any liability under the provisions of this paragraph;

(b) Any liability of the Authorities under this paragraph shall be reduced proportionately to the extent to which any costs, charges, damages and expenses are attributable to the neglect or default of Railtrack or of any person in its employ, or of its contractors or agents;

(c) Railtrack PLC shall give to the Authorities reasonable notice of any claim or demand as aforesaid and no settlement or compromise thereof shall be made without the prior consent of the Authorities:

The compensation payable under paragraph (19) above shall include a sum equivalent to the relevant costs;

(b) Subject to the terms of any agreement made between Railtrack and the relevant train operators regarding the terms of payment of the relevant costs in respect of that train operator, Railtrack shall promptly pay to each train operator the amount of any compensation which Railtrack PLC receives under this paragraph which relates to the relevant costs of that train operator;

(c) In this paragraph “relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any restriction of use of Railtrack’s railway network as a result of the construction or maintenance or failure of the relevant works or any such failure, act or omission as mentioned in paragraph (19) above;

(d) The obligation under this paragraph to pay Railtrack PLC the relevant costs shall, in the event of default, be enforceable direct by the train operators concerned:

(21) In the assessment of compensation payable under this section there shall not be taken into account any enhancement of that compensation attributable to any action taken by or any agreement entered into by Railtrack if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining compensation or increased compensation and for the avoidance of doubt any reference in this paragraph to compensation shall be deemed to relate to any payment due to Railtrack under this section:

(22) The Authorities and Railtrack may enter into, and carry into effect, agreements for the transfer to the Authorities of—

(a) any railway property shown on the deposited plan and described in the book of reference;

(b) any lands, works or other property held in connection with any such railway property; and

(c) any rights and obligations (whether or not statutory) of Railtrack relating to any railway property:

(23) Any difference arising between the Authorities and Railtrack under this section (other than a difference as to its meaning or construction) shall be determined by arbitration:

(24) As between the Authorities and Railtrack, section 65 (For protection of British Railways Board) of the Act of 1957 shall cease to have effect.

37 For protection of tele-communications operators

For the protection of telecommunications operators the following provisions shall, unless otherwise agreed in writing between the Authorities and the telecommunications operator concerned, have effect:—

(1) In this section unless the contrary intention appears expressions defined in the [1984 c. 12.] Telecommunications Act 1984 have the same meanings as in that Act and—

  • “apparatus” has the same meaning as in Part III of the Act of 1991; and

  • “relocation works” means works executed, or apparatus provided, under paragraph (5) below:

(2) The temporary stopping up or diversion of any street under section 24 (Temporary interference with highways) of this Act shall not affect any right of a telecommunications operator under paragraph 9 of the telecommunications code (contained in Schedule 2 to the Telecommunications Act 1984) to inspect, maintain, adjust, repair or alter any apparatus which, at the time of the stopping up or diversion, is in that street:

(3) Where a street is stopped up or diverted under section 20 (Supplementary works powers) of this Act any telecommunications operator whose apparatus is under, in, upon, over, along or across the street shall have the same powers and rights in respect of that apparatus, subject to the provisions of this section, as if this Act had not been passed:

(4) The Authorities shall give not less than 28 days' notice in writing of their intention to stop up or divert any street under section 20 (Supplementary works powers) of this Act to any telecommunications operator whose apparatus is under, in, upon, over, along or across the street:

(5) Where a notice under paragraph (4) above has been given, the telecommunications operator may, and if reasonably requested so to do by the Authorities in the notice, shall, as soon as reasonably practicable from the service of the notice—

(a) remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the telecommunications operator may reasonably determine and have power to place it; or

(b) provide other apparatus in substitution for the existing apparatus and place it in such position as aforesaid:

(6) Subject to the following provisions of this section, the Authorities shall pay to any telecommunications operator an amount equal to the cost reasonably incurred by the telecommunications operator in or in connection with—

(a) the execution of relocation works required in consequence of the stopping up or diversion of the street; and

(b) the doing of any other work or thing rendered necessary by the execution of relocation works:

(7) If in the course of the execution of relocation works under paragraph (5) above—

(a) apparatus of better type, or greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, or smaller capacity or of smaller dimensions, except where this has been solely due to using the nearest currently available type, capacity or dimension; or

(b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was;

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the Authorities, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this section would be payable to the telecommunications operator by virtue of paragraph (6) above shall be reduced by the amount of that excess:

(8) For the purposes of paragraph (7) above—

(a) an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as placing of apparatus of greater dimensions than those of the existing apparatus; and

(b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole shall be treated as if it also had been agreed or had been so determined:

(9) An amount which apart from this paragraph would be payable to a telecommunications operator in respect of works by virtue of paragraph (6) above (and having regard, where relevant, to paragraph (7) above) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7l/2 years earlier so as to confer on the telecommunications operator any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit as calculated in accordance with the Code of Practice entitled “Measures Necessary Where Apparatus is Affected by Major Works (Diversionary Works)” and dated June 1992, and approved by the Secretary of State on 30th June 1992 as revised and reissued from time to time:

(10) Paragraphs (6) to (9) above shall not apply where—

(a) the works constitute major bridge works for the purposes of Part III of the Act of 1991; or

(b) the works would if executed by the highway authority be major highway works within the definition of that Act;

but instead—

(i) the allowable costs of the relocation works shall be determined in accordance with section 85 of that Act (sharing of costs of necessary measures) and any regulations for the time being having effect under that section; and

(ii) the allowable costs shall be borne by the Authorities and the telecommunications operator in such proportions as may be prescribed by any such regulations:

(11) References in paragraph (10) above to section 85 of the Act of 1991 and regulations having effect thereunder are to that Act and any such regulations as having effect in accordance with section 3 (Application of the Act of 1991) of this Act.